The paving schedule proposed is:
- Monday-Mill Lake Ave from Excelsior Spring Ave to East Ave
- Tuesday-Mill Mystic Lane from Gilbert Rd to Conver Dr
- Wednesday-Pave Lake Ave from Excelsior Spring Ave to East Ave
- Thursday-Pave Mystic Lane from Gilbert Rd to Conver Dr
Paving will begin at 6:00 am and should be completed by 2:00 pm. There is no parking of cars on the street during these hours, and driveway access/egress will be limited with potentially length delays.
Please note that depending on construction circumstances or changing weather conditions this schedule could be revised. Thank you for your cooperation.