News Flash Home
The original item was published from 6/12/2019 11:44:04 AM to 6/14/2019 1:39:51 PM.

News Flash

Latest Information

Posted on: July 8, 2019

[ARCHIVED] Paving-Week of July 8, 2019

DumpTruck

The paving schedule proposed is:

Monday- Mill Seward Street from #50 Seward St (at man hole) Through Clement Ave Intersection to Denton Road

Monday-Mill Wells Street From Van Dam St to Waterbury St

Tuesday-Mill Ballston Ave from West Fenlon St to Lincoln Ave *East Bound Lane Only*

Wednesday- Pave Ballston Ave from West Fenlon St to Lincoln Ave *East Bound Lane Only*

Thursday- Pave Seward Street from #50 Seward St (at man hole) Through Clement Ave Intersection to Denton Road

Thursday-Pave Wells Street From Van Dam St to Waterbury St

Paving will begin at 6:00 am and should be completed by 2:00 pm. There is no parking of cars on the street during these hours and driveway access/egress will be limited with potentially lengthy delays.

Please note that depending on construction circumstances or changing weather conditions, this schedule could be revised. Thank You for your cooperation.