The paving schedule proposed is:
Monday-Mill Abie Drive from Marion Place to Diamond Place
Monday-Mill Diamond Place from Marion Place to Nelson Ave
Monday-Mill Pilkington Lane from Dead End to East Ave
Tuesday- Mill Granger Ave from Fifth Ave to Caroline Street
Wednesday- Pave Abie Drive from Marion Place to Diamond Place
Wednesday- Pave Diamond Place from Marion Place to Nelson Ave
Wednesday- Pave Pilkington Lane from Dead End to East Ave
Thursday- Pave Granger Ave from Fifth Ave to Caroline Street
Paving will begin at 6:00 am and should be completed by 2:00 pm. There is no parking of cars on the street during these hours and driveway access/egress will be limited with potentially lengthy delays.
Please note that depending on construction circumstances or changing weather conditions, this schedule could be revised. Thank You for your cooperation.