The paving schedule proposed is:
Monday-Mill Stratton St from White St to Lincoln Ave
Monday-Mill Ludlow St from Union Ave to Fifth Ave
Tuesday- Mill Lincoln Ave from Nelson Ave Intersection to Frank Sullivan Place past Siro's Restaurant
Tuesday- Mill Nelson Ave from 81 Nelson Ave to 37 Nelson Ave
Wednesday- Pave Stratton St from White St to Lincoln Ave
Wednesday- Pave Ludlow St from Union Ave to Fifth Ave
Thursday- Pave Lincoln Ave from Nelson Ave Intersection to Frank Sullivan Place past Siro's Restaurant
Thursday- Pave Nelson Ave from 81 Nelson Ave to 37 Nelson Ave
Paving will begin at 6:00 am and should be completed by 2:00 pm. There is no parking of cars on the street during these hours and driveway access/egress will be limited with potentially lengthy delays.
Please note that depending on construction circumstances or changing weather conditions, this schedule could be revised. Thank You for your cooperation.