The paving schedule proposed is:
Monday-Mill Round Table Road from Grand Ave to cul-de-sac
Tuesday- Mill Vichy Drive from Skidmore Drive to Hayes Drive
Wednesday- Pave Round Table Road from Grand Ave to cul-de-sac
Thursday- Pave Vichy Drive from Skidmore Drive to Hayes Drive
Paving will begin at 6:00 am and should be completed by 4:00 pm. There is no parking of cars on the street during these hours and driveway access/egress will be limited with potentially lengthy delays.
Please note that depending on construction circumstances or changing weather conditions, this schedule could be revised. Thank You for your cooperation.