The paving schedule proposed is:
Monday- Mill Granite St from Greenfield Ave to Alger St
Tuesday- Mill Trestle Ln from Van Dam St to Railroad Alley
Tuesday-Mill Railroad Alley from Van Dam St to Clinton St
Wednesday- Pave Granite St from Greenfield Ave to Alger St
Thursday- Pave Trestle Ln from Van Dam St to Railroad Alley
Thursday- Pave Railroad Alley from Van Dam St to Clinton St
Paving will begin at 6:00am and should be completed by 4:00pm. There is no parking of cars on the street during these hours and driveway access/egress will be limited with potentially lengthy delays. On the day of paving the road will be closed to all thru traffic until midafternoon.
Please note that depending on construction circumstances or changing weather conditions this schedule could be revised. Thank you for your cooperation.